JISD Bond Report Card - February

JISD Bond Report Card - February
Posted on 03/11/2019
This is the image for the news article titled JISD Bond Report Card - February

Great things are happening in the Jarrell Community!

In 2017, the Jarrell community overwhelmingly approved a bond proposal in the amount of $54 million to provide a new elementary school, as well as additions and improvements at Jarrell Middle School and Jarrell High School.

Here are highlights from the February Bond Report Card:

Igo Elementary School - Opening Fall of 2019

  • Groundbreaking was April 16, 2018
  • Project is 60% complete
  • Projected to be $3.8 million under budget

Jarrell Middle School Additions - Opening Spring of 2020

  • Construction began in October 2018
  • Project is 27% complete
  • Projects in on budget

Jarrell High School Additions & Renovations - Opening Fall of 2020

  • Construction began February 2019
  • Multi-phased project includes sitework, classroom addition, auditorium addition and renovations to cafeteria and library
  • Projected to be $2.2 million over budget. Costs overrun due to additional scope to address drainage and utility deficiencies and additional auditorium space.

JISD Bond Report Card - February 2

With savings from Igo Elementary, overall bond program is projected to be $1.5 million under budget.